MCQM5427 · [1] A factory uses 900 components per week. Supplier lead time is 3 weeks and the buffer stock is 1200 components. Stock on hand is 4500 components. How many additional weeks of production can run before the reorder level is reached? A1.3 weeksB2.0 weeksC3.7 weeksD5.0 weeks Next question →